sdarbinyan
821fecf5d3 docs: record Sprint 0.1 decisions across delivery plan, gap analysis, backend contract
Some checks failed
Architecture Governance / architecture (push) Has been cancelled
User answered 8 of 9 Sprint 0.1 blocking decisions (2026-08-17); backend
ownership stays open pending a clearer re-ask. Recorded and propagated:

- Payment chain unfrozen -> BACKEND-API-REFERENCE.md §7 and the Phase 1
  contract doc's status banner both updated; Phase 1/6/7 unblocked.
- No fixed external-marketplace list -> Phase 4's connector framework
  respecified as config-driven/generic; Sprint 4.2 retired as "per named
  marketplace," replaced with a generic onboarding runbook.
- FX rate source: ours, in-house, as the default (not just a fallback) ->
  Phase 1 contract's `source` field can read "internal" as the normal case.
- VK ID before OTP -> Phase 8 sprints resequenced (VK ID now 8.2, OTP 8.3).
- Multi-seller orders: unified -> Phase 3.3, Phase 5.2, and Z16 updated to
  the resolved model (one Order, per-seller Fulfillment groups).
- "Fixed 5-second payment" claim: confirmed non-issue, PAYMENT_POLL_INTERVAL_MS
  is already 5000 (real polling cadence, not an artificial delay).
- API namespace: new endpoints only (/api/v2/...), no forced migration of
  legacy endpoints.
- Document version: v3.1 is canonical.

Co-Authored-By: Claude Sonnet 5 <noreply@anthropic.com>
2026-08-17 22:08:23 +04:00
sdarbinyan
3c72c37e31 docs: v3.1 gap analysis + delivery plan; add DI seams to 9 admin gateways
Adds InjectionToken + factory for Orders, Products, Users, Transactions,
Monitoring, Moderation (mirrors existing Categories/Dashboard pattern) and
repoints their facades plus the derived Analytics/Customers facades and
admin-order-watcher off the mock LocalGateway class directly. No behavior
change today - still resolves to the mock - but a real backend can now be
bound per domain with zero facade edits.

Docs: full gap analysis of Product Plan v3.1 against current repo state,
and a phased delivery plan (10 phases, 34 sprints, 5 tracks) breaking every
identified gap into scoped, sequenced work.

Co-Authored-By: Claude Sonnet 5 <noreply@anthropic.com>
2026-08-17 21:24:57 +04:00